Mindanaotoday.com | NGCP lifts the implementation of MLDs
NGCP is pleased to announce the lifting of Manual Load Droppings (MLDs) effective 5:00PM, 29 November, on all 69KV lines servicing ZANECO, ZAMSURECO-1, ZAMSURECO-2, ZAMCELCO, MOELCI-1, MOELCI-2, and parts of LANECO.
Baloi-Aurora 138KV and Agus5-Aurora 138KV lines particularly between towers 22-23 are now cleared from tall-grown trees and hazardous vegetation after successful line clearing activities were completed yesterday, 29 November, in Brgy. Tingintingin, Kauswagan, Lanao del Norte.
NGCP thanks the local government of Lanao del Norte and the local law enforcement agencies for the support and assistance.
NGCP continues to appeal to the public not to plant along power line corridors to prevent prolonged power interruptions. (PR)
####